Loading...
Quick Links

Can\'t update date format

Home Forums Discussion Can\'t update date format

Tagged: 

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #412642 Reply

    Hi All,

    I’m using stand-alone project professional 2016. Project isn’t allowing me to change the date format — regardless of what I select in options, Project displays the format of:
    6/29/18 1:25PM.

    Any suggestions?

    Thanks,
    Mark

    #412643 Reply

    Something quick to check…
    Look at the view table definition. The view table definition allows you to set a date format on that specific view, which will override any default setting.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Can\'t update date format
Your information:




89 − = 88