Change Resource Calendar Using Bulk Edit or Not?

Home Forums Discussion Change Resource Calendar Using Bulk Edit or Not?

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #384709 Reply

    I have about 100 resources who need to be assigned the India holidays instead of the US ones. I created the new calendar. I expected to be able to select the resources in the Resource Center and then click BULK EDIT to change the calendar for all of them in one action. However, calendar is not a field which can be changed in BULK EDIT.

    How can I make calendar BULK EDITABLE?

    Thanks
    John

    #384710 Reply
    Larry Christofaro
    Participant

    Easiest way is to open them up in Microsoft Project (using the Open command in the Resource Center). Hope that helps.

    #384749 Reply

    Larry,

    YOU are the BEST!!!!!!

    Oh my, oh my … Thanks!

    John

    #384764 Reply
    Larry Christofaro
    Participant

    Thank you for the kind words. Glad it helped…