Changing duration in 2010

Home Forums Discussion Changing duration in 2010

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #6488 Reply
    Community
    Keymaster
    I normally insert the column "Type". This gives me the duration type for each activity and the ability to change to another type. Note, it doesn’t include the Effort Driven option.
    #5009 Reply
    Community
    Keymaster
    Without the built-in macros like 2007 had, what’s the easiest way to change an existing schedule’s duration type?  I’ve changed the settings under File > Options > Schedule but it didn’t change any of the task durations.
    Thanks,
    Ed
    #6493 Reply
    Community
    Keymaster
    The settings under File > Options > Schedule will only be taken into account for the newly created tasks. You’ll have the change the duration type for the already existing tasks ‘manually’ (like suggested using the Type column).
    #6507 Reply
    Community
    Keymaster
    Ed,
    Try File/Options/Add-ins and look for the Format Durations add-in.
    Mike Glen
    Project MVP (97-11)
    See http://tinyurl.com/2xbhc for my free Project Tutorials