Changing durations

Home Forums Discussion Forum Changing durations

Viewing 1 reply thread
  • Author
    Posts
    • #411750
      james buck long
      Guest

      Project Professional 2016
      Why do start and finish times change when the option Tasks are critical if slack is less than or equal to [ ] days. It was on 1, changing it to 0 or 2 changes start times? And changing start times are both the same using 0 or 2?

      Thanks in advance
      JBL

    • #411882
      Sam Huffman
      Guest

      James,
      That is not a lot of information to work with. If you are still having the problem, what troubleshooting steps have you already taken? If you solved the issue, what was causing the problem?

      I have been unable to reproduce with just the one change in settings that you reference. If constraints are in the schedule, that invariably causes issues as the dynamic schedule changes.

      I will create a blog entry and MPUG article soon regarding this, so stay tuned!

      Sam H