Home › Forums › Discussion › Color display for ripple effect due to schedule date changes
Tagged: Highlight Changes
Project typically shows a ripple or waterfall affect from a task date or duration change in the highlighted color blue.
Just recently my veriosn of Project has stopped highlighting changes. The changes stay white. Is there a way to turn highlights for changes back on? I am not sure how it stopped working in the first place.
This is Project 2010, and I do pull the most recent IMS version from a shared website.
Thank you…
I think if you go to Format/Text styles and select “changed cells” on “Item to change” (dropdown) you can modify the highlighting. Not sure why it changed, maybe someone selected “all”.
Jack — You were correct, “All” had been selected. Thanks so much for this quick fix!
Jody