Cost Accrual for Costs Incurred per Minimum 12 or 24 Hour Day

Home Forums Discussion Forum Cost Accrual for Costs Incurred per Minimum 12 or 24 Hour Day

Viewing 2 reply threads
  • Author
    Posts
    • #5079
      Karl Ozaeta
      Keymaster

      Working offshore in the Oil & Gas industry, we incur costs based upon a minimum 12-hour day for personnel and on a minimum 24-hour day for equipment.  Is there a way to keep MS Project 2007 (or any subsequent version) from pro-rating these costs over a scheduled day of lesser duration?  Changing Default Fixed Costs Accrual under Tools, Options, Calculations doesn’t seem to have the desired effect.

    • #6706
      Karl Ozaeta
      Keymaster

      I didn’t actually test this so I might be wrong but did you try using a 12 hour calendar?  You can also override this with a 24 hour task calendar for equipment.

    • #6748
      Karl Ozaeta
      Keymaster

      Thanks for your reply.  The calendar used doesn’t seem to matter.  If there is a partial day the resource is still pro-rated.  This normally occurs on the first day and last day of the project, but can sometimes occur during the project as well.