    Hi All,

    This is probably a very basic question. Forgive me, I am a PM university student navigating my way through MS project!

    Just something I have been stuck on for over an hour now! When I set up a 2 hr meeting in MS Project, I want it to give a cost of 2 hours per attendee (resource), not divided up between them all, as this is a case where more resources does not decrease the work time etc.
    I have tried unclicking effort driven tasks, fixing the duration, but nothing will stop the resources costs being divided by that 2 hrs!

    Can anyone please give me any hints or tips?!

    Thank you!

    #417657 Reply
    Jigs GatonJigs Gaton
    Member
    • Author
    • Forum Pro

    Yes. there is a panel under task, display task details, where all the resources are listed. Within that list u can assign hours to each person attending ur meeting. try that! Cheers, Jigs