Loading...
Quick Links

Creating Macros in Individual Schedules and creating an IMS

Home Forums Discussion Creating Macros in Individual Schedules and creating an IMS

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #417665 Reply
    Jamie NezbethJamie Nezbeth
    Participant

    I use MS Project Online-2016 and my Schedulers are considering creating Macros in their individual project schedules. I am responsible to create an IMS and update it weekly with these individual project schedules. Will it cause an issue if I merge all these MS project schedules into an IMS if all the schedules have different Macros created in them? How will this work?

    #417667 Reply

    Jamie,

    Thanks for drafting this questions, I was currently researching the same thing that you are asking . . .

    B.

    #417670 Reply
    Jamie NezbethJamie Nezbeth
    Guest

    Barry,

    I hope by asking, we can find some answers!!!! Let me know what you find out!!! I’ve been doing some research myself, and I can’t figure this out. I hope you can help!!

    Jamie

    #418248 Reply
    Minerva Goree
    Guest

    Hi Jamie,

    Let me see if I understand your question correctly. You seem to manage a master schedule with subprojects. These subprojects are files your team of schedulers owns. Also, it seems all the project files (master and subprojects) live in the Project Online environment.

    If I interpreted the situation correctly, then it is possible for each project file to have its own macros. When you insert a project file into your master as a subproject, you are basically just consuming raw data from the subprojects. You will not consume any of the local changes to their environment. Basically, the connection within the master are links to the subprojects.

    Hopefully, that helps.

    Minerva

    #418253 Reply
    Jamie NezbethJamie Nezbeth
    Participant

    Thanks Minerva! Yes it helps tremendously! At least now I know that whatever Macros they choose to have in their individual project schedules won’t affect the data in the IMS. Thanks so much for responding!!!!

    Jamie

Viewing 5 posts - 1 through 5 (of 5 total)
Reply To: Creating Macros in Individual Schedules and creating an IMS
Your information:




3 + 4 =