critical path ms project 2016 a lot task coming up with total lack =0

Home Forums Discussion critical path ms project 2016 a lot task coming up with total lack =0

  • This topic has 3 replies, 2 voices, and was last updated 2 years ago by Carlos Santos.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #414146 Reply
    Williams
    Guest

    “In MS Project 2016 how can one tell which of the tasks that appear on critical path are not all critical, in other words how can I tell which ones are not critical since they all have total slack = 0 days,I know for sure some are not critical but is there way other than testing with changing duration, manually ? I need to know this please help because spending hours testing one by one:

    #414152 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Williams, unfortunately they are all critical in the eyes of the Project formula. There are considerations based on rules. Constraints and deadlines affect critical path, maybe others I can’t remember but there are plenty of articles and videos that provide details. Hope that helps…

    #414153 Reply
    Tom Boyle
    Guest

    Williams,
    1. MS Project defines “Critical” tasks as those incomplete tasks with Total Slack <= 0. (You can increase but not decrease this threshold in the advanced options.) The collection of “Critical” tasks represents the true Critical (logic) Path under some very limited conditions; e.g. only one calendar, no constraints, no deadlines, no resource-leveling, no out-of-sequence progress.
    2. Assuming you’ve met other requirements of good scheduling practice (e.g. no “manually-scheduled” tasks, no inactive tasks, no logic on summaries, no logic open ends), then you should be able to define the Critical Path as the driving logic path to the project completion milestone. In MSP 2016 you can identify this path using the Task Path bar styles for “DrivingPredecessors.” It works fairly well for simple projects but is unreliable in the presence of logic that is not Finish-to-Start. It also fails in the presence of out-of-sequence progress and does not penetrate cross-project links (in linked master/sub-projects). If you need, here’s a Macro for Filtering based on “Task Path” in Microsoft Project: https://wp.me/p6CCB4-km.

    #414157 Reply
    Carlos Santos
    Guest

    Hi

    Please read this article.

    To Shorten The Critical Path