Custom fields: using them to combine fields and display the result in GANTT

Home Forums Discussion Custom fields: using them to combine fields and display the result in GANTT

Tagged: 

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #483979 Reply
    welshjs
    Participant

    I would like to display the task name followed by the start date. I used the following formula:
    [Name] & [Start]
    When I apply this custome field to the Bar Style text the text does not appear. If I choose any default field (Name, Start, Finish etc) it works fine.
    What am I doing wrong?
    I am using MSP 2019

    #483988 Reply
    Jerome Odeh
    Participant

    I entered your formula into Text1 custom field and was able to use it in Bar Style.

    I’m using Microsoft 2010

    #484017 Reply

    I use these Custom Fields on Task Bars often (MSP 2013).

    TEXT1 : [Name] & ” – ” & ([Duration]/480/5) & ” wks ”

    TExT2 : ProjDateConv([Finish],pjDate_mmm_dd) & ” (” & ([Duration]/480/5) & “wks) ”

    TEXT3 : [Name] & ” (” & ProjDateConv([Start],pjDate_mmm_dd) & “) “