Hi, please can someone help me:
I inserted some columns using formulas to calculate specific parameters useful for my plan.
For example in my work is important to understand eur/kilos for a project of steel manufacturing, I put in formula “cost/number” and it works correctly.
I made the same for another parameter which is productivity kilos/hours manufactured, I used a number/duration and it works but I don’t understand which number Project is calculating for to me.
Perhaps I don’t understand the exact meaning of the column “Duration”?
Thanks in advance for your support
Gian Luca
Gian, try thinking of duration in minutes by default in a formula and see if that help understand your results. Please respond with what you figure out. Thanks…
Yes! you’re right! The software shows into the cells “Hours” but the calculation works with “minutes” by default.
Thanks
Gian Luca
You are very welcome, and glad it helped…