    Dear Gents,

    Could you please help to choose right FUNCTION code in Formula section while editing custom field.
    I am trying to make some calculation however due the words (DAYS) in duration COLUMN the formula doesn’t work. That is why I would like to duplicate digits, numbers from duration column to another one in order to use formula.

    Thanks a lot in advance
    Your help and support are appreciated.

    Kindly
    Ramil

    #390450 Reply
    Larry Christofaro
    Participant

    Ramil, good question. Actually, the duration column in a formula works. It is only the display that shows the Days label. Duration is stored in minutes, so if you use it in a formula you may need to divide by 480 (if using the standard calendar) to get the number of days. Hope that helps…

    #390534 Reply
    Ramil
    Guest

    Thank you so much Dear Larry.

    Have a nice day.

    PS: I will be appreciated if you can help me with visual reports. I am trying to generate report by showing my custom fields.

    #390538 Reply
    Larry Christofaro
    Participant

    I wouldn’t call me an expert on the Visual Reports reporting function but you should be able to edit the template and add custom fields to the report from there…??