What is the formula and graphic indicator that I use if I want to compare the baseline finish date to the actual finish date to bring back indicators as followed.
actual finish is complete – blue
actual finish is late – red
actual finish is within 5 days of the baseline finish date – yellow
actual finish date is still more than 5 days in the future – green