    Hello Everyone!!

    I thought I posted this question yesterday but I don’t see it! Here goes one more time!!

    I’m working with Project 2010 Pro and 2013 Standard. I get to pick. My company is on a 4-4-5 fiscal accounting month. Is there a way to define the accounting month in either of these two versions of MSProject? If so how did you do this without using a 3rd party tool?

    Thank you so much!!!!

    Sandy

    #400583 Reply
    Larry Christofaro
    Participant

    Unfortunately there really isn’t a way to do this out of the box without using Project Online or Project Server. One way you can get data by fiscal month (I assume cost or work) is to export it to Excel by week (Visual Reports, Export, copy/paste, ??) Hope that helps…