Loading...
Quick Links

Displaying Remaining Work and Remaining Cost across time

Home Forums Discussion Displaying Remaining Work and Remaining Cost across time

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #9818 Reply
    Community
    Keymaster

    I am working in MSP 2003 and need to display Remaining Work and Remaining Cost across time. Any suggestions how I can do this?

    Rich Guard

    #9837 Reply
    Community
    Keymaster
    Hi Rich,
    To the best of my knowledge, this cannot be displayed in the MSOP Usage Grids.  You might try to export the work and actual work values using the analyze timescaled data in excel and do the math there.  It would be nice to be able to see remaining work and cost by month in project.
    Cheryl
Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Displaying Remaining Work and Remaining Cost across time
Your information:




75 + = 80