Durations entered in units other than days

Home Forums Discussion Forum Durations entered in units other than days

Viewing 4 reply threads
  • Author
    Posts
    • #4874
      lucas madeira
      Keymaster
      When attempting to use durations entered in units of months, weeks, e weeks, or e months we found that MSP does not forecast the finish date accurately. This has led us to set up a best practice of entering all of our durations in our projects in the unit of days or e days. Has anyone else come across this same issue?
    • #6104
      lucas madeira
      Keymaster
      I have used weeks and months in Project 2007 without any change to the project finish date.
    • #6168
      lucas madeira
      Keymaster
      I have not encountered the months and weeks issue in MSP. The company I work for follows the 8/80 rule for assigning duration. In most projects I have managed, I found this as a  good rule. It keeps my project tasks very manageable and easy to control.
      George del Carmen
    • #6170
      lucas madeira
      Keymaster
      I found a better way in managng the tasks and durations when entering units. Move all constraints dates to deadline. This way your finish date will not mess up.
      Yusuf Desai
    • #6169
      lucas madeira
      Keymaster
      Can you expand on the 8/80 rule? What exactly is it?

       

      Richard Berrish

Viewing 4 reply threads