Home › Forums › Discussion Forum › Error when try to edit Enterprise Calendar
Hi,
I’m working with a new install of Project Server 2013 (on Premise) and Project Professional 2013. Everything works fine and the connection is OK (f.i.: I can directly access schedules in PPro from PS, I can open schedules of PS projects from Ppro, and when I want to edit Resources starting from PS using the Ppro button that works fine).
However when I try to make a new Entrprise Calendar starting from PS, or edit an existing one I get the error message that Project Professional 2013 must be installed. I’m not able to work with Enterprise calendars starting from PS.
Does anyone have a clue what is going wrong and how to solve it?
Thanks in advance!!
Bob
Bob, check that all updates have been installed. This was a known issue that was recently fixed. The April CU has something on it but possibly more later. If you search you might also see a workaround, but I was having trouble finding it on a quick look. Good luck…