EVM WebNLearn Question

Home Forums Discussion EVM WebNLearn Question

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #262686 Reply
    Jim Forman
    Participant

    John, the Finish date for the “%Physical Complete” and #%Complete” projects were the same even though the EV’s (BCWP’s) were different. Why wasn’t the Finish date for the %Physical Complete project later than 7/24/15?

    #262862 Reply
    Community
    Keymaster

    Due to the amount of questions in today’s session, you will also have the opportunity to ask John your question in a “Part 2” session on Feb. 25th

    People who were registered for today’s session will automatically be registered for this second session

     