    Hi
    I use this formula to have the “expected (Theoretical) % complete” indicator important in my projects to compare with %complete

    expected &complete =If([finish]<=Now();”100″;IIf([start]>Now();0;int(0,5+100*(ProjDateDiff([start];Now())/[Duration])))) & “%”

    This is a text formula

    instead of Now() could use status day

    How can i compare both?
    Difference between both?
    expected %complete (text formula) – %complete(number)