Loading...
Quick Links

Export Task Usage View to Excel with a Custom Text Field??

Home Forums Discussion Export Task Usage View to Excel with a Custom Text Field??

Tagged: 

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #261831 Reply
    Heather Agee
    Member

    I have MS Project 2007. I want a pivot table in Excel of the Task Usage View. I use a customized text field lookup table for my WBS rather than the built-in WBS. So I want to see my resource loading by WBS (text field), by labor code.

    I have tried creating a visual report (new template) from task usage view but I can’t seem to pull in the labor codes if I can get the resource. The other option is to use the Baseline Work report and then I get labor codes but no custom field options. I tried to save as a MS Excel Pivot Table and I run into the same issues. Can anyone help?

Viewing 1 post (of 1 total)
Reply To: Export Task Usage View to Excel with a Custom Text Field??
Your information:




+ 52 = 53