    Resource usage, time phased by month is really useful. I have attempted to export this to Excel, but can only get the sum total planned and remaining planned hours by resource.

    I can see the data in MSP as I want to have it appear in Excel (actual work to date and remaining planned labor by individual resource), but am unable to get the data following the instructions provided.

    Please advise on what I can do this.

    Thanks.

    #415908 Reply
    Larry Christofaro
    Participant

    Kevin, not sure what instructions you are using but the data should be available. It sounds like you are asking for column data and not timephased data. If other options don’t work you might want to just copy entire columns and paste them into Excel…??