Exporting Lookup Tables

Home Forums Discussion Exporting Lookup Tables

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #5016 Reply
    Community
    Keymaster

    Is there a way to export a custom lookup table so that I can use it in any new Project file that I create without having to re enter the lookup table values?

    #6504 Reply
    Community
    Keymaster
    Great question.  Go to the lookup table of the custom field you want to create and choose the "Import Lookup Table" button on the bottem of that dialog box.  From there you can choose the project, the field type, and field to import.  You need to have the project that contains the lookup table opened when you perform this step.
    Hope that helps,
    Larry Christofaro