Loading...
Quick Links

Exporting resource unit timephased data to excel

Home Forums Discussion Exporting resource unit timephased data to excel

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #380875 Reply
    kamlesh Parmessur
    Participant

    Hello everyone

    Is there a way to export the resource unit assigned to task from project to excel (timephased data).
    Only the peak unit can be display in the task usage view and not the unit itself.

    can any body help me (even with VBA code is ok for me)

    I want to find out the number of resources required on a weekly basis for the complete duration of the project.

    #380879 Reply
    Larry Christofaro
    Participant

    Try adding the Percent Allocation detail style to the Resource Usage view. From the Resource Usage view, select Add Details form the Format ribbon. Find and add the Percent Allocation style. Roll up to Outline Level 1 (resource totals only). I hope this helps…

    #381535 Reply

    This might help if you can develop VBA Code
    https://msdn.microsoft.com/en-us/library/ee355231(v=office.12).aspx

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Exporting resource unit timephased data to excel
Your information:




36 + = 46