Hi
I m using MS Project 2016
I m not familiarized with Groups and filters.
How can I set a filter or a group that includes all the tasks or part of the tasks between two dates
ex: 12/26/2018 to 01/26/2019.
The Issue is: I want to have the the project cost in every 26Th day of each month. (should include all the tasks work and costs performed until the 2nd date)
Regards,
Carlos Santos
Hello,
Sounds like you just need to apply a date range filter. View Menu – Data Group – drop the filter menu down, select “Date Range…” Enter your start and finish dates.
Hi Heather Agee
Happy New Year!
Thanks for your answer.
It is for my Monthly Cash Flow (that should consider two dates: between month1, 25th to month2, 25th, and so on…)
The MS Project Report Monthly Cash Flow considers from day 1 to 30.
Regards,
Carlos