Filter out 0 days duration activities

Home Forums Discussion Filter out 0 days duration activities

Tagged: 

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #395080 Reply

    When I apply an auto-filter on the Duration column in Gantt View to sort out 0 duration tasks, some tasks that have duration on them (such as 35 days) also get removed from view. Has anyone run into this problem or have a solution? I double-checked that they are not marked “yes” for milestone and that I did not have any other filters or groups applied.

    I noticed this when I built a custom view and custom filter when I tried to use a manual filter to test that custom filter was working properly (by seeing if I got the same number of tasks). It seems my custom filter is working properly and my manual application of removing zero duration tasks is faulty by about 16 activities.

    #395215 Reply
    Larry Christofaro
    Participant

    Heather, interesting issue. I’ve never seen that before and can’t imagine it being a bug (but certainly not blaming it on a user issue either). Have you tried to have someone else do the same thing or you do the same on another machine? Let me know. This is crazy enough that I would be willing to take a look if you want another set of eyes. You can ping me on LinkedIn if you can’t find my email anywhere else.

Viewing 2 posts - 1 through 2 (of 2 total)