Fixed Duration with Expanded Start-Finish Dates?

Home Forums Discussion Forum Fixed Duration with Expanded Start-Finish Dates?

Tagged: , ,

Viewing 3 reply threads
  • Author
    Posts
    • #4980
      Deonne Schoner
      Keymaster
      Is there a way to show a Duration, for example, 100 hours, but have a Start and Finish Date that may expand 3-4 months?  We just need to show the duration hours over a period of time (and the customer does not want it in a spreadsheet).
      Thank you!!
    • #3727
      Deonne Schoner
      Keymaster
      Steve,
      I do not understand your question I’m afraid.
      Duration IS the time between start & finish…
      Do you mean effort of 100 hours spread over a period of 2 to 3 months? That’s what the Work field is for.
    • #6412
      Deonne Schoner
      Keymaster
      , I meant effort (work) hours spread over a period of 2 to 3 months and not duration.
    • #6413
      Deonne Schoner
      Keymaster
      you assign a resource either reduce units or specify the amount of work you want. So over 4w 80h of effort is units of 50%