    I have tasks which require us to travel to another location.  Consequently we want the task to start at the beginning of the week.  Other than that the standard calendar is fine.  Is there a way to tell Project to only start the task on a specific day of the week such as Monday?

    Joann

    #6684 Reply
    Community
    Keymaster

    Joann,

    If you want to keep the Monday date flexible to whatever Monday it lands on than you’ll need to create a calendar that is only active on Mondays and apply that calendar to the task.  Otherwise if you know the specific Monday than a simple constraint would be easier.

    Hope that helps…Larry Christofaro

    #10426 Reply
    Community
    Keymaster

    Constriant are there for this sort of cases.

    You can add MSO constraint. Yes, calendar can be there, but for your case, I think it will be an overkill.