Hello, iam currently using Ms Project 2016 stand alone, and iam trying to make schedule for construction project
iam having troube making formula in Ms Project to find out progress percentage of some task (this progress is base on value of money)
if iam using Excel the formula for this is “(Volume x base price) / Total Cost of the Project”
in Ms Project Formula “Total Cost of the Project” i input manually
is there a formula to input “Total Cost of the Project” automatic by using total sum of cost column?
Thank You