Loading...
Quick Links

Formulas and Graphical Indicators

Home Forums Customization Formulas and Graphical Indicators

  • This topic has 5 replies, 4 voices, and was last updated 3 months ago by Arumalor.
Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • #114162 Reply
    Ron
    Guest

    How to create formulas & stop light indicators based on % complete & start and finish dates. What I need is:
    BLUE if % complete is 100%
    GREEN if % complete is 99%
    YELLOW if % complete is > 0 (started) and between start and finish dates
    CLEAR if current date prior to scheduled start date
    RED if % complete = 0 and current date is > or = start date (prefer to compare to pro-rated completion % between start and finish date but not sure how to do this without getting too complex)
    RED if % complete < 99% and current date > finish date

    #114169 Reply
    CommunityCommunity
    Keymaster

    Hi Ron,

    Check out our Custom Formula guide, I think it is just what you’re looking for 🙂
    https://www.mpug.com/wp-content/uploads/2013/12/Customization-Formula-Guide-PDF-Version.pdf

    #409806 Reply

    Hi all,

    I am trying to add graphic indicators to my project plan following the instructions from the “ProjectWebv5.ppt” from Doug Bonebrake.

    MS Project doesn’t let me insert the warning formula `IIf([% Complete]<100,Switch(([Number3]
    <-5),3,[Number3]>=-5 And [Number3]<0,2,[Number3]>=0,1),3)` . I get a syntax error for the function “Switch”. Does anyone have an idea how to fix this?

    #409906 Reply
    John RiopelJohn Riopel
    Participant

    I tried this and it worked for me. IIf([% Complete]<100,Switch(([Number3]<-5),3,[Number3]>=-5 And [Number3]<0,2,[Number3]>=0,1),3)

    #409908 Reply

    Thanks John for testing. That’s strange. I can’t get this formula working in my MS Project 2010.

    #475343 Reply
    Arumalor
    Guest

    Book taxi to Brussels Airport (BRU). Comfortable taxi transfer to / from Brussels Airport. AtoB airport taxi will comfortably take you anywhere in Belgium.
    https://atobtransfer.com/brussels-belgium/atob-taxi-to-brussels-airport/
    https://www.facebook.com/transferservicebrussels/
    https://twitter.com/AtoB_transfer_

Viewing 6 posts - 1 through 6 (of 6 total)
Reply To: Formulas and Graphical Indicators
Your information:




64 − = 62