Loading...
Quick Links

Formulas in MS Project 2013

Home Forums Customization Formulas in MS Project 2013

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #409901 Reply
    Casi Gross
    Guest

    Is it possible to create a formula as follows? Start date – 10 days
    I have been asked to create two different schedules for each project to show different dates and I would like to make it a little more automated, if possible. Thanks.

    #409994 Reply
    John Williamson
    Guest

    Casi: you could insert a date field then use the formula: Start -10 then rename the field to Start 2, but may I suggest an alternative approach? If you are going to be using two schedules, you may want to click the Project tab, select Project Information, then offset the Start date of the second project by 10 days.

    Best,

    #414677 Reply
    stein milward
    Guest

    Casi:

    You can also use Baseline1 plan for this. Set your baseline 1 on your plan, then offset your plan by 10 days as John says.

    BR
    Stein Milward
    MS Project for bygg og anlegg
    http://www.msproject.no

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Formulas in MS Project 2013
Your information:




+ 54 = 64