Home › Forums › Discussion Forum › Gantt chart
Tagged: Gantt Chart, Microsoft Project 2010
How to print only Gantt chart from project2010? Also how to extract only Gantt chart portion(exclude task list)”
Sridhar Gandla PMPSRIDHARGANDLA
Best way to come close is to move the middle splitter bar to the far left, completely over the ID column. The resulting print will print the gantt chart with just the ID. Will that work or close enough? There are a couple of other options to help within Page Setup (under the print page) such as whether to print borders and legands. If that doesn’t work than there is a way to unlock the first column and put a blank column instead of the ID column. Hope that helps…
I had to change page settings as well to maximize the gantt view. I had to also reduce the task name column to basically be hidden. Without doing that, the task name would still appear even though the slide bar was all the way to the left.
I believe it will solve the problem…. Thanks Larry!