Loading...
Quick Links

Gantt Chart Bar Colors

Home Forums Discussion Gantt Chart Bar Colors

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #415947 Reply
    Jennifer K
    Guest

    I color coded my gantt chart dependent on resource. When the concrete labor crew resource is used, the bar changes to red, etc. However, when I add resource units to the task, the color changes back to black. Can anyone help with this?

    #416051 Reply
    Bob
    Guest

    The order you use in the chart where you define the color definition matters – try putting the condition for the concrete guys last or at the bottom of the chart then that will be the last condition read.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Gantt Chart Bar Colors
Your information:




55 − 51 =