    Jennifer K
    Guest

    I color coded my gantt chart dependent on resource. When the concrete labor crew resource is used, the bar changes to red, etc. However, when I add resource units to the task, the color changes back to black. Can anyone help with this?

    #416051 Reply
    Bob
    Guest

    The order you use in the chart where you define the color definition matters – try putting the condition for the concrete guys last or at the bottom of the chart then that will be the last condition read.