Home › Forums › Discussion Forum › Gantt Chart- rolling up colours
Hello,
Please view screenshot here: https://i.imgur.com/z3az9t8.png
Is it possible to make it so when I hide the summary, the bars at the top will have the same colours as each individual bar below? Currently they’re only coming up as blue and if I try to change the colour, it doesn’t allow me to change the colour of one single segment, only the entire bar.
If not, there any other way to make multiple segments different colours all in one line?
Thank you
Sylvia, first of all that is a very interesting way to rollup tasks. I like the break between tasks and having trouble repeating it. To answer your question from researching the bar styles I don’t see any option to color by task bar color. Would love to know how you created the splits between tasks on the summary line…:-)
I figured out how you got the splits in the summary rollup. You’re using 2010…correct? They changed the format of the Gantt bars to be flat instead of a rounded end which merges them together. Thanks…