Loading...
Quick Links

generic scheduling

Home Forums Discussion generic scheduling

This topic contains 3 replies, has 3 voices, and was last updated by  Stergios Kokkoris 6 days, 3 hours ago.

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #454575 Reply

    Stergios Kokkoris

    Dear colleagues,

    I am preparing a schedule for a client who is not sure for the project starting date. The schedule he wants is only for him to know the duration of the tasks.
    So, he needs a generic schedule with no specific starting date, the only information needed is duration of tasks and overall duration.

    On the timescale there are options for generic duration (weeks, days, etc. instead of calendar weeks, days, etc.). Can you please let me know if it is possible the generic scheduling to be depicted on the Gantt chart bars?

    Thank you in advance for your help

    best regards

    Stergios Kokkoris

    #454576 Reply
    Larry Christofaro
    Larry Christofaro
    Participant

    Hi Stergios, if you right click and select or double click the timeline header in the Gantt chart you have a couple of options for W1, W2 or Week 1, Week 2 under the Label drop-down. Hope that helps…

    #454655 Reply
    Jigs Gaton
    Jigs Gaton
    Member
    • Author
    • Forum Pro

    The Move Project start date click will also come in handy with this type of schedule, as after a few months the Gantt bars will be off the chart, in the past. Hit this button to put things back in view.

    #454714 Reply

    Stergios Kokkoris

    thanks Larry and Jigs, I appreciate your help

    stergios

Viewing 4 posts - 1 through 4 (of 4 total)
Reply To: generic scheduling
Your information: