  • #485843 Reply
    cbass1224
    Participant

    Hello. I’m using Project to schedule weekend work jobs on an hourly scale. The detail and role up look pretty good. But, I can’t figure out how to show real time progress. I think I can use a summary roll up complete through bar style to show status accurately. But I can’t get any line (progress line, today’s date, or project status) to show on the correct hour. Any tips on how to do this? Is there any option in the bar styles that will draw the bar correctly at today’s point in time down to the hour?

    #485927 Reply
    bobc455
    Member

    Well I’m not exactly sure what you are trying to show, but there is an option to include time in the date display. In my version of MS project:
    File ->
    Options ->
    General Tab ->
    Date Format (under the “Project View” section), select a format which includes time of day (in the format you’d like)

    -Bob C.