Loading...
Quick Links

How can I add/include the %Complete progress bar in a summary task?

Home Forums Discussion How can I add/include the %Complete progress bar in a summary task?

Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • #406514 Reply

    In earlier versions of MsProject I could show a bar under the roll-up summary task to visually show where the progress is at. It was particularly useful when showing the plan in the Outline 2/3 view

    #406515 Reply
    Jigs GatonJigs Gaton
    Guest

    Edgardo, you can edit the summary task display to show %xxx complete. Will that work for ya?

    #406516 Reply

    I know how to show the % Complete as a number (left or right of a summary task). What I am interested is a progress bar showing underneath the summary task bar

    #406517 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Edgardo, are you asking about a progress bar in the Gantt chart? I don’t remember any version that shows a progress for summary tasks, but you can add that to the Gantt view by using the Bar Styles option. Go to the Format ribbon, Format, Bar Styles. Copy the current Progress Bar style to a new line under the existing styles, and enter the contents of the Show For…Tasks similar to the Summary Task or Manual Summary task. Hope that helps…

    #406518 Reply

    Great, Thanks Larry! I found that you also need to change the “To” setting (right column) to % Complete. With this a progress bar is being shown across the summary task with the % complete

    #406520 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    You are welcome, glad it helped…

Viewing 6 posts - 1 through 6 (of 6 total)
Reply To: How can I add/include the %Complete progress bar in a summary task?
Your information:




96 − 86 =