How can I determine the priority when entering actuals in MSP 2013?
It appears that depending on the relationships on the tasks and the order I enter the data I get different results.
For example if I have a task with a FF relationship and I enter 10h of actual work and reaming work 0, I get 99% complete
It will not allow me to enter 100% complete. However if I enter an Actual Finish date into the task it will enter 100% complete.
Good question. I know there is/was a bug that under certain circumstances, Project will not calculate 100% but I thought it was in relationship to marking tasks as scheduled (or something like that). Try changing remaining duration to 0 and see if that will work. I can’t seem to recreate it right now. Hope that helps…