Home Forums Discussion How can I highlight days on the time scale with out making them non working days

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #113099 Reply
    Garry
    Guest

    Hi All

    How can I highlight certain days, as appears with non working days, on the time scale. I would like to highlight certain days + weeks in which certain tasks nee to be competed + it would be of great benifit if I could see that in the gantt.
    thanks a million.

    #114280 Reply
    Larry Christofaro
    Participant

    Unfortunately your specific item can’t be done. You can setup deadlines to indicate days that certain tasks need to be complete.