How can I transfer data from custom cost column to fixed cost

Home Forums Discussion How can I transfer data from custom cost column to fixed cost

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #400150 Reply
    Guy Forget
    Guest

    I added 4 custom cost columns, one of which show the total of 3 others. How can I transfer data from that customized column to fixed cost column for the 300 tasks of my project.
    Thanks for your help!
    Guy

    #400153 Reply
    Larry Christofaro
    Participant

    Guy, you should be able to copy the entire total cost column and then select and paste it to the Fixed Cost column. Hope that helps…