  • #408578 Reply

    We have an environment where are requested projects are kept in a SharePoint list.
    At a certain point, we would like to create a PWA project from the data kept on the list.
    Can someone point me in the right direction on how to do that? Please.

    Thanks..

    #408579 Reply
    Larry Christofaro
    Participant

    Norman, do a search on Project Server Ideation and you will find a lot of information. Basically, if you put the SharePoint list within the PWA site collection (as a list in PWA or in a sub-site), you will see a ribbon option to create a project. Mapping fields correctly is the key. Good luck…

    #408580 Reply

    Thanks Larry, you are always insightful.

    Sorry, but I failed to mention that the list is not in the PWA domain. It is under a Team Site.

    #408581 Reply
    Larry Christofaro
    Participant

    That’s the trick. The list needs to be under PWA, otherwise it doesn’t work.