  • #412963 Reply

    Hi All and Happy Friday.

    I have a project that I’m (for the first time ever) using resource leveling. Trying to understand how project calculates the number so I can interpret its meaning. If project displays 24ehrs as the leveling delay, should I interpret that as:
    1) a three business day delay (given an 8 hour work day)?
    2) a one business day delay (given 24 hours per day)?

    Thanks in advance,
    Mark

    #412965 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Robert, glad to see you’re giving leveling a try. It takes a bit to learn and be comfortable with it, but if you can get through that you’ll never go back. There are several MPUG recorded webinars that can help, including a three-part series I did a while back. It was a while ago but the function hasn’t changed.

    Now, about that ehrs. Not sure where you are seeing that but e means elapsed which means all time. So, 24 ehrs is a 24 hour day, even if it isn’t a business day.

    Hope that helps…

    #412966 Reply

    Thanks, Larry. That is the answer that I thought it was… just need to know for sure. Have a great weekend.

    Mark