Loading...
Quick Links

how to add weekends as a workday to my gannt chart ?

Home Forums Discussion how to add weekends as a workday to my gannt chart ?

Viewing 7 posts - 1 through 7 (of 7 total)
  • Author
    Posts
  • #139100 Reply
    Tuğçe
    Guest

    Hi, i m a new user of ms project 2013. i m trying to prepare my own schedule, but program ignores the weekends. i want to change it. could you please somebody help me to fix this? thanks 🙂

    #139183 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    You can add weekends by setting up the standard calendar. Use the Change Working Time in the Project ribbon. Go to the Work Weeks tab and set Saturday and Sunday to the appropriate working times. Hope this helps…

    #139210 Reply
    Szabolcs
    Guest

    Hello, i would like to ask nearly the same. I have created a one-year project with subprojects, and the program takes off weekends from time intervallums. I would like to see the WHOLE project with weekend days. How can i set this? Thank you in advance.

    #139212 Reply
    Szabolcs
    Guest

    Larry’s advice did not work at all 🙁

    #139470 Reply
    #139712 Reply
    Szabolcs
    Guest

    I could do it, thank you.

    #392535 Reply
    Rick Yoder
    Guest

    When I build a 6 work day calendar to include Saturdays in my work week and I set the calendar for a task in the advance tab, to 6 day work Calendar…my task using the 6 day calendar start having 1/2 days or partial days show up on the Guant Chart.
    How do I correct this?
    Note: I use MS Project for scheduling construction projects…we don’t use the Resource Loading or Hours…we strictly use whole days.

Viewing 7 posts - 1 through 7 (of 7 total)
Reply To: how to add weekends as a workday to my gannt chart ?
Your information: