How to flag summary tasks?

Home Forums Discussion Forum How to flag summary tasks?

Viewing 4 reply threads
  • Author
    Posts
    • #477363
      cbass1224
      Participant

      Hello, all. Does anyone know how to flag summary tasks? I want to flag them based on the summary task name. I would have thought either [Name]=”” or [Task Summary Name]=”” would do it. But neither work. [Name] only applies to actual tasks with that name, and [Task Summary Name] applies to all subtasks underneath the summary with that name.

    • #477366
      Tom Boyle
      Guest

      Should work. Have you checked “Use formula” for “Calculation for task and group summary rows” on the custom field specification?

    • #477368
      cbass1224
      Participant

      No, I had not. And that was the problem. Thank you very much!

    • #477371
      Daryl Deffler
      Guest

      Not certain why you’re trying to flag them, but there is a task field called “Summary”. It’s a Yes/No field and it already identifies the task as a summary.

    • #477413
      cbass1224
      Participant

      I’m formatting summary tasks based on the name. Thanks for your input.