How to move linked .mpp files?

Home Forums Discussion How to move linked .mpp files?

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #478407 Reply
    bobc455
    Member

    I recently started at a new company. So far all of my .mpp files are on my own computer- and we all know what a bad plan that is.

    I would like to move to a company server, however most of my files are linked to a Resource .mpp file and from what I understand those links include the local path.

    How to I move my .mpp files to another directory and preserve or update the links between project files?

    Thanks!

    -Bob C.

    #478408 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    BobC, good question. Go ahead and move the projects and resource pool to the new location. Then do the following:
    * Open the resource pool and all projects you want to link (or a few at at time)
    * Select Resource Pool / Share Resources, select each of the existing links and break the link
    * Open each project you want to link, select Share Resources, and reselect the resource pool
    Hope this helps…

    #478424 Reply
    Jigs GatonJigs Gaton
    Member
    • Author
    • Forum Pro

    OR use a cloud service that honors ur local file system, like Dropbox and many others. Install that, and you should not have to re-link anything. (Other issues arise, but related to the cloud in general).This may be a useful tact if you have hundreds or more files to relink.

    #478489 Reply
    Eric UyttewaalEric Uyttewaal
    Guest

    Hi, I would like to add what Larry and Jigs wrote. The linked files appear in the Microsoft Project interface as if they are absolute path references (i.e. “C:\My Documents\MyProject.MPP”), but, in fact, they are relative path references (i.e. “Look in the same directory/folder for this file” or “Go one directory/folder level up and then one level down into “\My Projects” to look for this file name”). This means that, if you move a whole system of linked files from one directory/folder to another directory/folder, you would never need to re-link those files.
    BTW I describe in detail how to work with linked files and shared resource pools in my textbook ‘Forecasting Programs’. Thanks!

    #478934 Reply
    bobc455
    Member

    Larry, Jigs, and Eric-

    Just wanted to post a quick note of thanks! I did as Eric suggested and moved them all together, it worked perfectly. I didn’t have to break & re-create the links.

    -Bob C.