  • #416396 Reply
    Bob Hillier
    Participant

    I baselined my initial schedule. I have a change request and need to re-baseline the changed tasks. I want to save the orginal baseline and then set a new baseline. Is there a way to rename the original baseline that I have save. It is currently called Baseline 1 (last saved on date ….)?
    I would like to call it “Initial baseline”.

    #416404 Reply
    Sai Prasad
    Participant
    • Community Leader
    • Forum Pro

    This is not possible. You can’t rename the labels Baseline, …, Baseline 10. Your latest baseline should be saved in Baseline, as values stored in this baseline set is used for variance calculation. Baseline 1, …, Baseline 10 is used to store the previous baselines. So, to take a backup/copy of your current baseline, in Set Baseline dialog choose Set Interim Plan with Copy from as Baseline and To as Baseline 1.