Loading...
Quick Links

How to roll up using the WBS Code

Home Forums Discussion How to roll up using the WBS Code

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #30929 Reply

    I did a WBS dictionary and in many of my projects I am using the same codes in any sites (i.e. requirements gathering – WBS Code 1.2.3). I am using this code wherever I need to gather requirements, but how can I roll up so I now the combined or summarized requirements gathering effort and summarized start and end dates?

    #30936 Reply
    Paul Ibarra
    Guest

    One way is to use the Group function in MS Project.  By creating a Group that keys on the WBS along with a cutomized View you can generate a roll up of your WBS accounts which will summarize (roll up) data and allow you to produce a report.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: How to roll up using the WBS Code
Your information:




− 4 = 2