Loading...
Quick Links

How to schedule estimated start date MS Pro 2010

Home Forums Discussion How to schedule estimated start date MS Pro 2010

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #90058 Reply
    Rosemary
    Participant

    Is there a Best Practice to track and follow estimated Planned Start Dates in tasks? We are using “TBD-01/31/2014″ in the Planned Start field when a customer is not sure when the task is to begin, but the PM must put the task in the schedule.
    Are there any issues with doing it the “TBD-01/31/2014″ way?

    Are there other suggestions for tracking these estimated dates?

    #90313 Reply
    Sai PrasadSai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Hi Rosemary,

    I can provide two options
    Option 1:
    I suppose you have the Task Mode field set to Manually Scheduled. In this mode, Project will not calculate the dates and you are free to enter user-defined start, finish and duration. So, it is fine to have TBD-01/31/2014 in the Start field when you are not sure when the task will begin.

    For manually scheduled tasks, if you want to see the recommended start and finish date based on dependencies, calendars and other factors then insert Scheduled Start and Scheduled Finish. Scheduled Start and Scheduled Finish are read-only.

    Option 2:
    Have your task as auto scheduled. Let Project calculate the start and finish based on dependencies, calendars and other factors. If the date is not yet confirmed, you can have custom field like Start1/Flag1 to indicate this date is tentative.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: How to schedule estimated start date MS Pro 2010
Your information:




48 − = 41