Loading...
Quick Links

How to show % Complete of a particular task in EPM Project Center view

Home Forums Discussion How to show % Complete of a particular task in EPM Project Center view

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #198900 Reply
    Calvin Zhang
    Participant

    In EPM project center, there is an existing “% Complete” column showing an overall project completion status. If I would like to show a “% complete of a particular subtask” for every project, how to set it up in Server Settings? I am using MS Project 2010.

Viewing 1 post (of 1 total)
Reply To: How to show % Complete of a particular task in EPM Project Center view
Your information: