Home › Forums › Discussion Forum › I am trying to get a visual report out of MSP and MSP 2010 cannot find Excel.
Hi, I am trying to get a visual report out of MSP 2010. Each time I try it gives me an error telling me that it needs Excel 2007 or greater. I have Excel 2013 loaded, but this does not seem to be getting recognised by MSP2010.
From Ellen Lehnert, via MPUG LinkedIn:
The problem is a mismatch of levels. MSP 2010 will not see Excel 2013. even though the error message is misleading, your Excel is at a higher level than msp.
Ellen in correct. KB article that provides some additional information here: https://support.microsoft.com/en-us/kb/2863707